CIPAceTM HelpProject Task Status Management |
Top |
|
Navigate Here: Projects > Browse Implementation Projects > select a Project > Click the Project Status tab > Select a Project Status > and click the Edit icon
You can edit a Project Status record on the Project Status Management page.
To edit a project status record, update any of the following fields:
The required fields are noted with an asterisk (*).
Project*: The corresponding project's ID and name. It is read only.
Implementation Status*: The status of the project implementation. There are four statuses: In Construction, In Design, Pending/On-Hold, and Procurement.
Schedule Status*: The status of the project schedule. There are four statuses: Behind Schedule, Completed, On Hold, and On Schedule.
Percent Completed: It is the % of Completion field on the Manage Task page of the corresponding task.
Status Date*: The date when the task status was tracked.
Completion Date: The date when the task will be completed.
Schedule: Specify a schedule of the implementation project.
Task: Select a task to track its status. All tasks in the corresponding project schedule are listed for selection.
Summary: The overall summary of the project status.
Notes: Description of the project status.
Picture File Name: Click the Browse button to browse and select a file to upload to the task. The picture size is limited to 1MB.
Click the Save button to save the changes and the system will go to the Browse Project Statuses page.
Click the Delete button to delete the project status record.
Click the Cancel button to clear the latest input. |
| ______________________________________________________ |
| Copyright © 2002- CIPPlannerTM Corp. |