CIPAceTM HelpAdd Task |
Top Previous Next |
Navigate Here: Enter into Schedule Gantt Chart, click Add Task icon on the tool bar
A new task will be added to the bottom of the task list, with an auto-generated # (Task Order No.), a Task ID and default values for Task Name, Task Mode, Start Date, Finish Date and Duration.
Navigate Here: Right click an existing task and select Add... option in the menu
Six Add operations will be displayed: Task above, Task below, Milestone, Sub-task, Successor, and Predecessor.
❖Task above: Add a new task above the selected task. The Start Date, Finish Date and Duration of this new task will be the same as the selected task. ❖Task below: Add a new task below the selected task. The Start Date, Finish Date and Duration of this new task will be the same as the selected task. ❖Milestone: Add a new milestone task below the selected task. The Start Date, Finish Date of this new task will be the same as the Finish Date of the selected task. ❖Sub-task: Add a new sub-task below the selected task. The Start Date, Finish Date and Duration of this new task will be the same as the selected task. ❖Successor: Add a new task below the selected task. The new task is the successor of the selected task by Finish-To-Start relationship. ❖Predecessor: Add a new task above the selected task. The new task is the predecessor of the selected task by Finish-To-Start relationship .
You must click the Save icon on the tool bar to save all new tasks.
|
______________________________________________________ |
Copyright © 2002- CIPPlannerTM Corp. |