CIPAceTM Help

Add Task

Top  Previous  Next

Navigate Here: Enter into Schedule Gantt Chart, click Add Task icon add on the tool bar

 

A new task will be added to the bottom of the task list, with an auto-generated # (Task Order No.), a Task ID and default values for Task Name, Task Mode, Start Date, Finish Date and Duration.

 

GanttChart_AddNewTask

 

Navigate Here: Right click an existing task and select Add... option in the menu

 

Six Add operations will be displayed: Task above, Task below, Milestone, Sub-task, Successor, and Predecessor.

 

GanttChart_AddNewTaskbyMenu

 

Task above: Add a new task above the selected task.  The Start Date, Finish Date and Duration of this new task will be the same as the selected task.

Task below: Add a new task below the selected task.  The Start Date, Finish Date and Duration of this new task will be the same as the selected task.

Milestone: Add a new milestone task below the selected task.  The Start Date, Finish Date of this new task will be the same as the Finish Date of the selected task.

Sub-task: Add a new sub-task below the selected task.   The Start Date, Finish Date and Duration of this new task will be the same as the selected task.

Successor: Add a new task below the selected task.  The new task is the successor of the selected task by Finish-To-Start relationship.

Predecessor: Add a new task above the selected task.  The new task is the predecessor of the selected task by Finish-To-Start relationship .

 

You must click the Save icon Save on the tool bar to save all new tasks.

 

______________________________________________________
Copyright © 2002- CIPPlannerTM Corp.