CIPAceTM Help

Manage Project CORs

Top  Previous  Next

Navigate Here: Projects > Browse Implementation Projects; select a Project > Click the RFPs tab

 

You can browse and manage the Change Order Requests (COR) associated with the current implementation project on the CORs tab page.

 

Project Management_CORs

 

A brief summary of each attribute displays in the table. The summary includes: COR ID, Subject, Primary Project, Project Contract, Contractor, Issue Date and Status.  You can sort the attributes by clicking the linked column headers. If there are too many records to display, you can use the navigation control to view another page.

 

You can quickly find the records you wanted by using the search function. Enter search conditions in the search fields and click the Search button. The COR data grid will show the records that match the search conditions. Click the Reset button to clear the conditions in the search fields.

 

Click the Edit icon Edit at the end of the row or the hyperlinks under COR ID and Subject. The system will then open Edit COR General screen.

 

Click the Add icon Add and the system will open the Add Change Order Request screen. The primary project will be pre-filled as the current project.

 

You can associate COR(s) with the current project by clicking Associate. The system will pop up a window for selecting COR(s), listing all CORs in the system except those already associated with the current project.

 

You can disassociate COR(s) with the current project by selecting the COR(s) and clicking DisAssociate. Please note that it’s not allowed to disassociate the COR whose Primary Project is the current project.

______________________________________________________
Copyright © 2002- CIPPlannerTM Corp.