Navigate Here: Projects > Browse Projects; select a project > Implementation tab > Schedules tab; Enter into Schedule Gantt Chart, click Reports icon on the tool bar
You can select and print below standard or custom reports to track project schedule progress.
❖Standard Reports
❑Project Task Schedule and Notes Report
❖Custom Reports
❑Project Schedule Baselines Comparison Report
You can select multiple schedule baselines to compare with the current project schedule, and click the View Report button to open or save the Excel file as shown below.
❑Project Schedule Task Status Report
You can select multiple schedules under different projects, and click the View Report button to open or save the Excel file as shown below.
Note: For a master schedule, all its sub schedules (no matter selected or not) and their tasks will be included in the master schedule task hierarchy structure.
You can find how CIPAce enables you to create new custom reports in Custom Report Management.
|