Navigate Here: Projects > Browse Projects; select a project > Implementation tab > Schedules tab; Enter into Schedule Gantt Chart, click Reports icon report on the tool bar

 

You can select and print below standard or custom reports to track project schedule progress.

 

Standard Reports

 

Project Schedule Report

Project Task Schedule and Notes Report

 

Custom Reports

 

Project Schedule Baselines Comparison Report

 

RptProjectScheduleBaselinesComparison

 

You can select multiple schedule baselines to compare with the current project schedule, and click the View Report button to open or save the Excel file as shown below.

 

RptProjectScheduleBaselinesComparisonCapt

 

Project Schedule Task Status Report

 

RptProjectScheduleTaskStatusReport

 

You can select multiple schedules under different projects, and click the View Report button to open or save the Excel file as shown below.

 

RptProjectScheduleTaskStatusReportCapt

 

Note: For a master schedule, all its sub schedules (no matter selected or not) and their tasks will be included in the master schedule task hierarchy structure.

 

You can find how CIPAce enables you to create new custom reports in Custom Report Management.

 

 